PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED217254

Building

5412 Park Pl, Edina

IssuedDec 18, 2024
StatusUnknown
Value$750,000
Inspections30
Scope of work

New, NEW HOME

Location context
Parcel1902824120003
Coordinates44.90477, -93.33439
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$3,750
Total paid$3,750
Timeline
ApprovedDec 13, 2024
IssuedDec 18, 2024
Inspection record
Inspections30
Passed28
Failed0
  1. Mar 23, 2026

    Tree Final (call 952-826-0308)

    Approved

    InspectorLaura Beres

    Planted 1 new tree.
  2. Mar 17, 2026

    Escrow

    Progress Report

    InspectorLindsay Evans

    Nate sent contractor escrow refund link via email
  3. Mar 17, 2026

    Bldg Progress

    Progress Report

    InspectorNate Borwege

    This permit is being taken over by permit ED246643. Contractor will not be completing any remaining work. All future inspections are under permit ED246643.
  4. Nov 25, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorAndy Reinisch

    Fall 2025 seasonal - items addressed
  5. Nov 20, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorAndy Reinisch

    Dumpster is full and needs to be emptied.
  6. Oct 29, 2025

    Engineering (call 952-903-5728)

    Not Approved

    InspectorAndy Reinisch

    Curb stop needs to be adjusted. Locate pop-up on east side. Pay for driveway permit. Locate infiltration trench intake
  7. Aug 25, 2025

    Lath

    Approved

    InspectorGodwin Annin

  8. Jun 6, 2025

    Insulation

    Approved

    InspectorGodwin Annin

  9. Jun 6, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Site sign missing Clean up street along entire front of site Remove LP tank
  10. Jun 5, 2025

    Insulation

    Partial Approval

    InspectorScot Jandro

    main and upper floors ok Basement not ready
  11. Jun 3, 2025

    Framing

    Approved

    InspectorTedd Nelson

    - Add a squash block above lower level egress window on the north side
  12. Apr 1, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Site sign is missing Need to clean off driveway and street along the curb in front of site *Also need to have a permit for the LP tank on site
  13. Apr 1, 2025

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    Safety fence no longer needed
  14. Mar 11, 2025

    Floor Slab

    Approved

    InspectorTedd Nelson

    - Vapor barrier and 2" foam for the basement
  15. Feb 20, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  16. Feb 20, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  17. Jan 24, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Clean up street and remove all sediment track out.
  18. Jan 24, 2025

    Construction Fence

    Not Approved

    InspectorLindsay Evans

    Tighten up safety fence in areas where sagging
  19. Jan 15, 2025

    Foundation Pre-Backfil

    Approved

    InspectorBrian Crask

  20. Jan 15, 2025

    Foundation Pre-backfil (Top of foundation survey)

    Approved

    InspectorBrian Crask

  21. Jan 15, 2025

    Poured Foundation Reinforcement

    Approved

    InspectorBrian Crask

    Revised engineering was submitted and approved for section of foundation under the tall wall.
  22. Jan 10, 2025

    Construction Fence

    Not Approved

    InspectorScot Jandro

    fence is missing in areas
  23. Jan 10, 2025

    Foundation Pre-Backfil

    Partial Approval

    InspectorScot Jandro

    Pending poured foundation inspection on 1/6/25 Pending TOF as-built survey
  24. Jan 6, 2025

    Poured Foundation Reinforcement

    Not Approved

    InspectorBrian Crask

    -Tall wall at front right corner of the home is 8" thick, not 10" thick per plan. Need revised engineering for this change. Everything else is OK
  25. Dec 31, 2024

    Construction Fence

    Approved

    InspectorLindsay Evans

Show 5 earlier inspections
  1. Dec 31, 2024

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  2. Dec 30, 2024

    Footing

    Approved

    InspectorTedd Nelson

  3. Dec 26, 2024

    Shoring needs to be done before footing inspection

    Approved

    InspectorTedd Nelson

  4. Dec 20, 2024

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    Just getting started on new home. No steep slopes at this time. Install safety fence as soon as steep slopes are present on-site.
  5. Dec 20, 2024

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.