Permit / Edina← Search
#ED217178Building
5125 Edina Industrial Blvd 600, Edina
IssuedJan 7, 2025
StatusUnknown
Value$275,000
Inspections12
Scope of work
New Tenant Finish, Hangry Joes Chicken
Location context
Parcel0911621340011
Coordinates44.86344, -93.35484
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$1,375
Total paid$1,375
Timeline
ApprovedJan 6, 2025
IssuedJan 7, 2025
Inspection record
Inspections12
Passed10
Failed0
- Aug 28, 2025
Building Final - COMMERCIAL
ApprovedInspectorRick Chase
Addresses posted
- Apr 8, 2025
Building Final - COMMERCIAL
Approved, w/ CommentsInspectorRick Chase
Owner/occupant required to locate/place addresses numbers as directed by Building Official due to the subway space splitting.
- Apr 3, 2025
Building Final - COMMERCIAL
Not ApprovedInspectorRick Chase
egress lighting not functional in common hallway. Can pass final inspection when lighting is operational.
- Apr 1, 2025
Fire Dept final
ApprovedInspectorBrian Hanrahan
- Mar 25, 2025
Fire Sprinkler Final (For appt: 952-826-0339)
Approved, w/ CommentsInspectorBrian Hanrahan
-heads were added in Subway hallway and CO2 closet
- Mar 17, 2025
Fire Sprinkler Final (For appt: 952-826-0339)
Approved, w/ CommentsInspectorBrian Hanrahan
-heads to be added in Subway hallway and also one in CO2 closet by back exit
- Mar 17, 2025
Fire Dept final
Progress ReportInspectorBrian Hanrahan
-verify sprinkler heads installed
- Mar 14, 2025
Above Ceiling Grid
Partial ApprovalInspectorTedd Nelson
- Finish the grid around the hood...maintain proper clearances
- Mar 14, 2025
Fire Sprinkler Rough-In (add`l permit req`d)
Partial Approval w/ CommentsInspectorBrian Hanrahan
-hallway for bathrooms needs sprinkler head added by Subway door. Unsure at this time who is responsible
- Mar 14, 2025
Bldg Progress
Progress ReportInspectorTedd Nelson
- Need to provide the clearances to non-combustible and combustibles for the new hood. - Not sure if a full framing inspection was done, all was complete during my above ceiling inspection. - Lift Bridge Builders did not build the demising walls only interior and the bulk head
- Feb 20, 2025
Framing-Commercial
Partial ApprovalInspectorPeter Akmenkalns
1. need approved plan on site 2. mech permit not issued yet. ok to cover common walls and cash wrap
- Feb 19, 2025
Framing-Commercial
Not ApprovedInspectorPeter Akmenkalns
1. need approved city plans on site 2. frp on common walls needs to be blocked in wall so gyp can be patched 3 Mech permit not issued yet. need approved plan and inspections 4. electriucal RI needed 5 remove old beverage line sin subway wall
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.