Permit / Edina← Search
#ED215135Building
10 Southdale Ctr 2764, Edina
IssuedJan 22, 2025
StatusUnknown
Value$500,000
Inspections14
Scope of work
Alteration/Remodel, Commercial Tenant Improvement
Location context
Fees & payments
Total fees$375
Total paid$375
Timeline
ApprovedJan 14, 2025
IssuedJan 22, 2025
Inspection record
Inspections14
Passed11
Failed0
- Aug 11, 2025
Building Final - COMMERCIAL
ApprovedInspectorTedd Nelson
- Jul 28, 2025
Fire Dept final
Progress ReportInspectorBrian Hanrahan
-it was noted that FDC missing outside horn/strobe -Cobeck aware also -under Viking permit
- Jun 30, 2025
Temporary CO
ApprovedInspectorTedd Nelson
- South exterior wall to be completed and final the sign permit
- Jun 26, 2025
Building Final - COMMERCIAL
Not ApprovedInspectorTedd Nelson
- Tile 48" in the wet wall areas in the restroom required - Install sign to remain open... - Provide signage at the accessible fitting room. - Mechanical final required - Provide smoke control report - Exit passage must be cleared out of ALL construction materials - Widen temp. opening at exit passage doors
- Jun 26, 2025
Fire Dept final
Partial ApprovalInspectorBrian Hanrahan
- Jun 26, 2025
Smoke Control
Progress ReportInspectorBrian Hanrahan
-smoke exhaust tested good per Summit (Matt). Report to be submitted.
- May 15, 2025
Bldg Progress
Progress ReportInspectorTedd Nelson
- Meeting with JS for items needed for a final approval. MEP and Fire approval. Summit smoke evac test result required. All life safety and accessibility complete. - The exit passage on the east will need to have ALL materials cleared out and fence to be installed for the flow of egress to comply - Can not block the door to Kowalski's that is an exit for the assembly
- May 8, 2025
Above Ceiling Grid
ApprovedInspectorTedd Nelson
- May 6, 2025
Fire Sprinkler Final (For appt: 952-826-0339)
ApprovedInspectorBrian Hanrahan
- Apr 9, 2025
Framing-Commercial
ApprovedInspectorTedd Nelson
- Back/south wall framing
- Apr 1, 2025
Above Ceiling Grid
Partial ApprovalInspectorTedd Nelson
- Ceiling framing
- Apr 1, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Embeds and one #5 bar for the store front curb
- Apr 1, 2025
Framing-Commercial
Partial ApprovalInspectorTedd Nelson
- Structural C-channel for the new RTU's. contractor will provide the SI report
- Mar 11, 2025
Framing-Commercial
Partial ApprovalInspectorTedd Nelson
- light gauge steel stud walls. - Provide Plumbing RI inspection - Install grab bar backing and fire stop floor penetrations - Run the gyp. to the deck for the el cove to maintain continuity for the 1 hr rating. - Framing for the store front/show room on the north end not complete
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.