#ED215135

Building

10 Southdale Ctr 2764, Edina

IssuedJan 22, 2025
StatusUnknown
Value$500,000
Inspections14
Scope of work

Alteration/Remodel, Commercial Tenant Improvement

Location context
Fees & payments
Total fees$375
Total paid$375
Timeline
ApprovedJan 14, 2025
IssuedJan 22, 2025
Inspection record
Inspections14
Passed11
Failed0
  1. Aug 11, 2025

    Building Final - COMMERCIAL

    Approved

    InspectorTedd Nelson

  2. Jul 28, 2025

    Fire Dept final

    Progress Report

    InspectorBrian Hanrahan

    -it was noted that FDC missing outside horn/strobe -Cobeck aware also -under Viking permit
  3. Jun 30, 2025

    Temporary CO

    Approved

    InspectorTedd Nelson

    - South exterior wall to be completed and final the sign permit
  4. Jun 26, 2025

    Building Final - COMMERCIAL

    Not Approved

    InspectorTedd Nelson

    - Tile 48" in the wet wall areas in the restroom required - Install sign to remain open... - Provide signage at the accessible fitting room. - Mechanical final required - Provide smoke control report - Exit passage must be cleared out of ALL construction materials - Widen temp. opening at exit passage doors
  5. Jun 26, 2025

    Fire Dept final

    Partial Approval

    InspectorBrian Hanrahan

  6. Jun 26, 2025

    Smoke Control

    Progress Report

    InspectorBrian Hanrahan

    -smoke exhaust tested good per Summit (Matt). Report to be submitted.
  7. May 15, 2025

    Bldg Progress

    Progress Report

    InspectorTedd Nelson

    - Meeting with JS for items needed for a final approval. MEP and Fire approval. Summit smoke evac test result required. All life safety and accessibility complete. - The exit passage on the east will need to have ALL materials cleared out and fence to be installed for the flow of egress to comply - Can not block the door to Kowalski's that is an exit for the assembly
  8. May 8, 2025

    Above Ceiling Grid

    Approved

    InspectorTedd Nelson

  9. May 6, 2025

    Fire Sprinkler Final (For appt: 952-826-0339)

    Approved

    InspectorBrian Hanrahan

  10. Apr 9, 2025

    Framing-Commercial

    Approved

    InspectorTedd Nelson

    - Back/south wall framing
  11. Apr 1, 2025

    Above Ceiling Grid

    Partial Approval

    InspectorTedd Nelson

    - Ceiling framing
  12. Apr 1, 2025

    Footing

    Partial Approval

    InspectorTedd Nelson

    - Embeds and one #5 bar for the store front curb
  13. Apr 1, 2025

    Framing-Commercial

    Partial Approval

    InspectorTedd Nelson

    - Structural C-channel for the new RTU's. contractor will provide the SI report
  14. Mar 11, 2025

    Framing-Commercial

    Partial Approval

    InspectorTedd Nelson

    - light gauge steel stud walls. - Provide Plumbing RI inspection - Install grab bar backing and fire stop floor penetrations - Run the gyp. to the deck for the el cove to maintain continuity for the 1 hr rating. - Framing for the store front/show room on the north end not complete

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.