#ED216985

Building

10 Southdale Ctr 2870A, Edina

IssuedJan 23, 2025
StatusUnknown
Value$274,989
Inspections5
Scope of work

Alteration/Remodel, Tumi Tennant Finish

Fees & payments
Total fees$1,000
Total paid$1,000
Timeline
ApprovedJan 23, 2025
IssuedJan 23, 2025
Inspection record
Inspections5
Passed5
Failed0
  1. May 15, 2025

    Building Final - COMMERCIAL

    Approved

    InspectorTedd Nelson

  2. May 7, 2025

    Fire Dept final

    Approved, w/ Comments

    InspectorBrian Hanrahan

    -smoke exhaust tested good by Summit. Values > 3. -Fire alarm good.
  3. Apr 7, 2025

    Building Final - COMMERCIAL

    Not Approved

    InspectorTedd Nelson

    - Remove thumb turns and add verbiage to remain unlocked - Provide mechanical final - Smoke EVAC/BAS system to be working and finaled from Summit. - Shell permit 2151833 for Cobeck needs to be complete and finaled - Remove exit sign or mirror on door to rear stock area
  4. Feb 20, 2025

    Framing-Commercial

    Partial Approval

    InspectorPeter Akmenkalns

    1. electricla RI required 2. fire RI required.
  5. Jan 30, 2025

    Fire Sprinkler Final (For appt: 952-826-0339)

    Approved

    InspectorBrian Hanrahan

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.