Building
6004 Ewing Ave S, Edina
New, New Home Escrow PAID
- Sep 9, 2025
Escrow
Approved, w/ CommentsInspectorLindsay Evans
OK to issue escrow refund. Completed Fund Transfer for outstanding fees to be deducted from escrow and sent to Finance.
- Sep 9, 2025
Building Final
Approved, w/ CommentsInspectorNate Borwege
Escrow refund of $9590 Approved.
- Sep 5, 2025
Escrow
Progress ReportInspectorLindsay Evans
Conducted final site inspection. Took final new home pics and uploaded to PDox. IP has been removed. Per Water Resources: Per City records, a well is unlikely on the lot. If a well is encountered during construction, it must meet the rules set in the City’s Private Well Policy.
- Sep 4, 2025
Final-NEW HOME
ApprovedInspectorScot Jandro
C of O sent
- Sep 4, 2025
Escrow
Progress ReportInspectorLindsay Evans
Sent contractor an email with the link for escrow refund.
- Aug 20, 2025
Tree Final (call 952-826-0308)
ApprovedInspectorLaura Beres
Planted 5 new trees.
- Aug 20, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Aug 4, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Aug 4, 2025
Residential Redevelopment Coordinator
ApprovedInspectorLindsay Evans
- Aug 1, 2025
Planning
ApprovedInspectorKris Aaker
- Aug 1, 2025
Final As Built Survey
Progress ReportInspectorScot Jandro
As-built survey saved to PIMS and Lot survey FFE892.8400 vs proposed 892.8762 Sent to engineering, forestry, and planning
- Jul 28, 2025
Final-NEW HOME
Progress ReportInspectorScot Jandro
Sent back final as-built to get FFE on survey Address is complete Obtain final approvals from forestry, planning, engineering (will forward final as-built survey when updated)
- Jul 23, 2025
Engineering (call 952-903-5728)
ApprovedInspectorAndy Reinisch
- Jul 18, 2025
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
Exterior complete and site stabilized. Site sign gone but house numbers installed. Occupied.
- Jul 10, 2025
Temporary CO
ApprovedInspectorErin Rust
CC ran in office for temp co. Good until 8/10/25.
- Jul 8, 2025
Blower Door Test (Air Leakage)
Approved, w/ CommentsInspectorScot Jandro
1.10 ach
- Jul 8, 2025
Engineering (call 952-903-5728)
Not ApprovedInspectorAndy Reinisch
*Adjust grading to prevent drainage from entering property to the south. *Add 2" air gap for sump discharge. *Confirm sump connection was made *Establish turf, remove erosion control, clean street *Locate curb stop after sod is placed.
- Jul 8, 2025
Final-NEW HOME
Partial ApprovalInspectorScot Jandro
Install address Complete sod and landscaping obtain approvals from planning, engineering and forestry
- Jul 3, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jul 2, 2025
Final-NEW HOME
Not ApprovedInspectorGodwin Annin
- Pending Final As Built Survey - Pending blower door test report - Egress ladder required in the basement - Deck install in the backyard not ready
- Jun 20, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jun 2, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- May 30, 2025
Lath
ApprovedInspectorBrian Crask
- May 15, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Corrections made but LP tank still on-site
- May 12, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Spring Inspection: Need to install rock entrance Clean sediment and debris in street Remove LP tank
Show 18 earlier inspections
- Apr 29, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Apr 21, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Same conditions as previous EC inspection
- Apr 16, 2025
Insulation
ApprovedInspectorPeter Akmenkalns
- Apr 11, 2025
Framing-New Home
ApprovedInspectorGodwin Annin
- Apr 9, 2025
Foundation Pre-backfil (Top of foundation survey)
ApprovedInspectorBrian Crask
As-Built TOF survey has been submitted, approved and saved to PIMs Photos & Lot Surveys.
- Apr 7, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
No change from inspection on 4/1/25
- Apr 4, 2025
Bldg Progress
Progress ReportInspectorNate Borwege
Met with Contractor from Castle Gate construction. Advised that the measurement at the bottom of the main floor stairwell will be measured from the riser to the wall (not from nosing to the wall). I also advised that the Foundation pre backfill inspection is incomplete and that a TOF as-built survey is required to be submitted to Brian Crask.
- Apr 1, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Need to clean sediment and debris from street Need to install a rock entrance *Note: there was a road closure sign at the intersection but no record of street closure request submitted
- Mar 18, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Mar 4, 2025
Foundation Pre-Backfil
Partial ApprovalInspectorBrian Crask
-Ok to backfill front and front half of each side. Back and back half of each side still needs rock added. -Need As-Built TOF Survey for full approval
- Mar 3, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorAndy Reinisch
Visited site, very large stockpile with single bio log to protect. No issues at time of visit
- Feb 28, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Feb 28, 2025
Poured Foundation Reinforcement
ApprovedInspectorTedd Nelson
- Feb 28, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
House has been demo'd. Large stockpile in front w/only single row bio logs. Sent to Andy to assess Monday.
- Feb 27, 2025
Footing
ApprovedInspectorTedd Nelson
- Feb 24, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Still working on demo
- Feb 11, 2025
Tree Protection (call 952-826-0308)
ApprovedInspectorLaura Beres
- Jan 23, 2025
Tree Plan
Approved, w/ CommentsInspectorLindsay Evans
See Tree escrow permit- NRMP ED218089; preserving 3 trees, removing 10 trees; 3 trees require mitigation. LB