PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED218425

Building

6004 Ewing Ave S, Edina

IssuedFeb 24, 2025
StatusUnknown
Value$897,000
Inspections43
Scope of work

New, New Home Escrow PAID

Location context
Parcel2002824330037
Coordinates44.89416, -93.32780
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$3,375
Total paid$3,375
Timeline
ApprovedFeb 24, 2025
IssuedFeb 24, 2025
Inspection record
Inspections43
Passed34
Failed0
  1. Sep 9, 2025

    Escrow

    Approved, w/ Comments

    InspectorLindsay Evans

    OK to issue escrow refund. Completed Fund Transfer for outstanding fees to be deducted from escrow and sent to Finance.
  2. Sep 9, 2025

    Building Final

    Approved, w/ Comments

    InspectorNate Borwege

    Escrow refund of $9590 Approved.
  3. Sep 5, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Conducted final site inspection. Took final new home pics and uploaded to PDox. IP has been removed. Per Water Resources: Per City records, a well is unlikely on the lot. If a well is encountered during construction, it must meet the rules set in the City’s Private Well Policy.
  4. Sep 4, 2025

    Final-NEW HOME

    Approved

    InspectorScot Jandro

    C of O sent
  5. Sep 4, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Sent contractor an email with the link for escrow refund.
  6. Aug 20, 2025

    Tree Final (call 952-826-0308)

    Approved

    InspectorLaura Beres

    Planted 5 new trees.
  7. Aug 20, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  8. Aug 4, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  9. Aug 4, 2025

    Residential Redevelopment Coordinator

    Approved

    InspectorLindsay Evans

  10. Aug 1, 2025

    Planning

    Approved

    InspectorKris Aaker

  11. Aug 1, 2025

    Final As Built Survey

    Progress Report

    InspectorScot Jandro

    As-built survey saved to PIMS and Lot survey FFE892.8400 vs proposed 892.8762 Sent to engineering, forestry, and planning
  12. Jul 28, 2025

    Final-NEW HOME

    Progress Report

    InspectorScot Jandro

    Sent back final as-built to get FFE on survey Address is complete Obtain final approvals from forestry, planning, engineering (will forward final as-built survey when updated)
  13. Jul 23, 2025

    Engineering (call 952-903-5728)

    Approved

    InspectorAndy Reinisch

  14. Jul 18, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Exterior complete and site stabilized. Site sign gone but house numbers installed. Occupied.
  15. Jul 10, 2025

    Temporary CO

    Approved

    InspectorErin Rust

    CC ran in office for temp co. Good until 8/10/25.
  16. Jul 8, 2025

    Blower Door Test (Air Leakage)

    Approved, w/ Comments

    InspectorScot Jandro

    1.10 ach
  17. Jul 8, 2025

    Engineering (call 952-903-5728)

    Not Approved

    InspectorAndy Reinisch

    *Adjust grading to prevent drainage from entering property to the south. *Add 2" air gap for sump discharge. *Confirm sump connection was made *Establish turf, remove erosion control, clean street *Locate curb stop after sod is placed.
  18. Jul 8, 2025

    Final-NEW HOME

    Partial Approval

    InspectorScot Jandro

    Install address Complete sod and landscaping obtain approvals from planning, engineering and forestry
  19. Jul 3, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  20. Jul 2, 2025

    Final-NEW HOME

    Not Approved

    InspectorGodwin Annin

    - Pending Final As Built Survey - Pending blower door test report - Egress ladder required in the basement - Deck install in the backyard not ready
  21. Jun 20, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  22. Jun 2, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  23. May 30, 2025

    Lath

    Approved

    InspectorBrian Crask

  24. May 15, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Corrections made but LP tank still on-site
  25. May 12, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Spring Inspection: Need to install rock entrance Clean sediment and debris in street Remove LP tank
Show 18 earlier inspections
  1. Apr 29, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  2. Apr 21, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Same conditions as previous EC inspection
  3. Apr 16, 2025

    Insulation

    Approved

    InspectorPeter Akmenkalns

  4. Apr 11, 2025

    Framing-New Home

    Approved

    InspectorGodwin Annin

  5. Apr 9, 2025

    Foundation Pre-backfil (Top of foundation survey)

    Approved

    InspectorBrian Crask

    As-Built TOF survey has been submitted, approved and saved to PIMs Photos & Lot Surveys.
  6. Apr 7, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    No change from inspection on 4/1/25
  7. Apr 4, 2025

    Bldg Progress

    Progress Report

    InspectorNate Borwege

    Met with Contractor from Castle Gate construction. Advised that the measurement at the bottom of the main floor stairwell will be measured from the riser to the wall (not from nosing to the wall). I also advised that the Foundation pre backfill inspection is incomplete and that a TOF as-built survey is required to be submitted to Brian Crask.
  8. Apr 1, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Need to clean sediment and debris from street Need to install a rock entrance *Note: there was a road closure sign at the intersection but no record of street closure request submitted
  9. Mar 18, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  10. Mar 4, 2025

    Foundation Pre-Backfil

    Partial Approval

    InspectorBrian Crask

    -Ok to backfill front and front half of each side. Back and back half of each side still needs rock added. -Need As-Built TOF Survey for full approval
  11. Mar 3, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorAndy Reinisch

    Visited site, very large stockpile with single bio log to protect. No issues at time of visit
  12. Feb 28, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  13. Feb 28, 2025

    Poured Foundation Reinforcement

    Approved

    InspectorTedd Nelson

  14. Feb 28, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    House has been demo'd. Large stockpile in front w/only single row bio logs. Sent to Andy to assess Monday.
  15. Feb 27, 2025

    Footing

    Approved

    InspectorTedd Nelson

  16. Feb 24, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Still working on demo
  17. Feb 11, 2025

    Tree Protection (call 952-826-0308)

    Approved

    InspectorLaura Beres

  18. Jan 23, 2025

    Tree Plan

    Approved, w/ Comments

    InspectorLindsay Evans

    See Tree escrow permit- NRMP ED218089; preserving 3 trees, removing 10 trees; 3 trees require mitigation. LB

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.