Building
5523 Park Pl, Edina
New, New Home with deck: Escrow Paid
- Feb 4, 2026
Escrow
Progress ReportInspectorLindsay Evans
Conducted final site inspection - everything looked good. Took final New Home pics and uploaded to PDox. Verified IP has been removed.
- Dec 30, 2025
Escrow
Progress ReportInspectorLindsay Evans
Per Water Resources: Per City records, a well is unlikely on the lot. If a well is encountered during construction, it must meet the rules set in the City’s Private Well Policy.
- Dec 22, 2025
Escrow
Progress ReportInspectorLindsay Evans
Received online escrow refund request. Working to process.
- Nov 20, 2025
Residential Redevelopment Coordinator
Progress ReportInspectorLindsay Evans
- Nov 19, 2025
Residential Redevelopment Coordinator
Progress ReportInspectorLindsay Evans
- Nov 17, 2025
Residential Redevelopment Coordinator
Approved, w/ CommentsInspectorLindsay Evans
- Nov 17, 2025
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
Seasonal Inspection - Fall OK IP removed, all exterior completed, overall looks good.
- Nov 12, 2025
Engineering (call 952-903-5728)
ApprovedInspectorAndy Reinisch
- Nov 12, 2025
Final-NEW HOME
ApprovedInspectorPeter Akmenkalns
- Nov 10, 2025
Final-NEW HOME
Partial ApprovalInspectorPeter Akmenkalns
need enginnering final then ok to issue CO
- Nov 6, 2025
Tree Final (call 952-826-0308)
ApprovedInspectorLaura Beres
Planted 49 new trees. Tree escrow paid.
- Nov 6, 2025
Blower Door Test (Air Leakage)
ApprovedInspectorScot Jandro
ACH 1.80
- Nov 6, 2025
Final As Built Survey
ApprovedInspectorScot Jandro
FFE 875.4000 vs proposed 875.5000 saved to PIMS and Lot survey sent to engineering, forestry and planning.
- Nov 6, 2025
Planning
ApprovedInspectorKris Aaker
- Nov 5, 2025
Tree Final (call 952-826-0308)
Not ApprovedInspectorLaura Beres
Pending payment of outstanding tree escrow to approve the tree final.
- Nov 5, 2025
Final-NEW HOME
Not ApprovedInspectorScot Jandro
-Install interior railing -Draft stop mech ceiling -Provide Elec. final -Provide blower door test -Provide Finall as-built survey -Close permit ED225927 for RPZ Obtain final approval from engineering, planning, and forestry
- Aug 20, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Aug 4, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jul 17, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jun 30, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jun 12, 2025
Lath
ApprovedInspectorPeter Akmenkalns
- Jun 10, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Jun 6, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- May 29, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- May 29, 2025
Framing-New Home
ApprovedInspectorGodwin Annin
Show 18 earlier inspections
- May 29, 2025
Insulation
Approved, w/ CommentsInspectorGodwin Annin
- Insulation inspection Approved. - Framing corrections not done....Contractor not on site to go over corrections
- May 21, 2025
Weather Barrier/Flashing
ApprovedInspectorBrian Crask
- May 21, 2025
Framing-New Home
Not ApprovedInspectorBrian Crask
-Need floor slab inspection approved -Need truss heal blocked at braced wall panels -Add stud under squash block in basement at back wall -Add two squash blocks under point load from header at center bearing wall.
- May 12, 2025
Erosion Ctrl/Const Entrance
Approved, w/ CommentsInspectorLindsay Evans
Spring Inspection: Site looked good. Clean up street near entrance/exit at end of day.
- May 7, 2025
Residential Redevelopment Coordinator
No Physical Inspection DoneInspectorLindsay Evans
- Apr 29, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Apr 29, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Apr 17, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Apr 17, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Apr 1, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Apr 1, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Mar 20, 2025
Foundation Pre-Backfil
ApprovedInspectorBrian Crask
- Mar 20, 2025
Foundation Pre-backfil (Top of foundation survey)
ApprovedInspectorBrian Crask
As-Built TOF survey has been submitted, approved, and saved to Lot Surveys and PIMs Photos.
- Mar 18, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Mar 18, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Mar 13, 2025
Poured Foundation Reinforcement
ApprovedInspectorGodwin Annin
- Mar 12, 2025
Footing
ApprovedInspectorGodwin Annin
- Mar 12, 2025
Shoring needs to be done before footing inspection
ApprovedInspectorGodwin Annin
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.