PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED218835

Building

6136 Oaklawn Ave, Edina

IssuedApr 11, 2025
StatusUnknown
Value$10,000
Inspections35
Scope of work

Other Demolition (645-649), DEMO HOME - escrow paid

Location context
Parcel1902824430075
Coordinates44.89197, -93.33665
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$50
Total paid$50
Timeline
ApprovedApr 10, 2025
IssuedApr 11, 2025
Inspection record
Inspections35
Passed15
Failed0
  1. Aug 26, 2025

    Demo Final

    Approved, w/ Comments

    InspectorLindsay Evans

    Received photo from contractor (per Nate's request) showing site conditions after the garage had been demo'd and floor slab removed prior to building the new retaining wall and backfilling the area.
  2. Aug 26, 2025

    Escrow

    Approved, w/ Comments

    InspectorLindsay Evans

    OK to issue escrow refund. Per Water Resources: Per City records, a well is unlikely on the lot. If a well is encountered during construction, it must meet the rules set in the City’s Private Well Policy.
  3. Aug 26, 2025

    Building Final

    Approved, w/ Comments

    InspectorNate Borwege

    Escrow refund of $2500 Approved.
  4. Aug 21, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Received pic from contractor and forwarded to Nate for review to verify whether or not its sufficient in place of Demo Final on garage area.
  5. Aug 15, 2025

    Erosion Ctrl/Const Entrance

    No Inspection Required

    InspectorLindsay Evans

    Correction from 8/14/25 will be followed through on under the NH permit
  6. Aug 15, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

  7. Aug 14, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Replenish rock entrance Clean up street Replace bio logs along curb and driveway entrance Replace missing sections of bio logs in various along left (south) side of site Install bio logs along the back (where old garage has been removed)
  8. Aug 13, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Received online escrow refund request. Working to process. *Last item we were waiting on was for garage demo (as that was scheduled to be completed at a later date, so I will verify this before processing.
  9. Jul 24, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  10. Jul 18, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Replenish rock entrance Clean up sediment that has tracked out into the street
  11. Jul 7, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  12. Jul 1, 2025

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    No longer needed at this time
  13. Jul 1, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Bio logs near entrance are damaged and need to be replaced
  14. Jun 24, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Rock has been replenished. Other items still need to be corrected.
  15. Jun 18, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    Replenish rock entrance Replace bio logs that are broken near entrance Clean up street where dirt and sediment has tracked out
  16. Jun 18, 2025

    Construction Fence

    Progress Report

    InspectorLindsay Evans

    Safety fence was up but entire front was open and no workers on-site. Needs to be closed when not actively working.
  17. Jun 12, 2025

    Demo Final

    Progress Report

    InspectorLindsay Evans

    No inspection conducted for Demo Final. Using the Approved Footing inspection that Peter did on the New Home permit #ED218855 on 6/12/25. *Applies only to the area of existing house. Garage has not been demo'd yet.
  18. Jun 9, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  19. Jun 9, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Overall, the site looked good but need to replenish rock in entrance - I notified Al.
  20. Jun 5, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Met Al Richter on-site to discuss overall site conditions and expectations. Reiterated all items Andy noted on 6/4/25 and will follow up again tomorrow. *Al will notify me when they plan to demo garage as they need to coordinate w/adjacent sites
  21. Jun 5, 2025

    Construction Fence

    Progress Report

    InspectorLindsay Evans

    Showed exactly where safety fence needed to be installed by the end of the day (as there will be steep slopes and required at that point). Explained that it needs to remain installed until backfilled and 1st floor completed.
  22. Jun 4, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Andy conducted a follow up inspection. Improvement but still need some corrections. *Note: Rock entrance has been installed -Bio logs missing and damaged - need to replace -Sediment and rock spilling over curb into street w/no EC barrier - needs to get pulled back onto site and proper EC established -Significant sediment build up along the curbline - needs to get removed and swept -Majority of the street had been cleaned but there are still areas that need to be swept more
  23. Jun 3, 2025

    Erosion Ctrl/Const Entrance

    Not Approved

    InspectorLindsay Evans

    No proper entrance - need to install rock entrance Sediment tracked out into the street (over a block in both directions) - needs to get cleaned up immediately Bio logs along the front and near entrance/exit no longer visible or functioning - need to replace all that are damaged and/or missing
  24. Jun 2, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Have not started demo on this house yet
  25. May 29, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Not started
Show 10 earlier inspections
  1. May 15, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Overall, site looks good. Have not started demo yet.
  2. Apr 29, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Haven't started yet
  3. Apr 17, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Have not started demo
  4. Apr 11, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Have not started yet.
  5. Apr 4, 2025

    Tree Plan

    Approved, w/ Comments

    InspectorLindsay Evans

    See tree escrow permit- NRMP ED219433, preserving 3 trees, removing 4 - no mitigation required. LB
  6. Mar 24, 2025

    Preconstruction

    Approved, w/ Comments

    InspectorLindsay Evans

    Received pic of Site Sign showing larger numbers have been installed Also had a conversation with Al about the plan with existing tuck under garage on back side of the property. Per Water Resources: Per City records, a well is unlikely on the lot. If a well is encountered during construction, it must meet the rules set in the City’s Private Well Policy.
  7. Mar 24, 2025

    Residential Redevelopment Coordinator

    No Inspection Required

    InspectorLindsay Evans

    Site restoration plan submitted during demo permit review. Required to have the following inspections upon completion of the demo and prior to receiving the escrow refund. - Inspection of hole after removal of all debris prior to filling (Building Inspections, 952-826-0372) - Demo Final after filling hole and appropriate grading is complete (Building Inspections, 952-826-0372) - Engineering Final after stabilizing all disturbed soils (Engineering Dept. 952-903-5728) - Tree Final (Forestry Dept. 952-826-0308)
  8. Mar 18, 2025

    Preconstruction

    Not Approved

    InspectorLindsay Evans

    Conducted follow up Pre-Demo inspection. Took additional photos and uploaded to PDox. *Numbers on Site Sign do not meet required size and need to be updated Need clarification on the plan with the back garage area and how that factors into the demo process or what will remain in-tact.
  9. Mar 18, 2025

    Tree Protection (call 952-826-0308)

    Progress Report

    InspectorLindsay Evans

    Tree plan has not been approved yet so cant not verify tree protection at same time as Pre Demo inspection.
  10. Mar 14, 2025

    Preconstruction

    Progress Report

    InspectorAndy Reinisch

    Site is approved for demo. EC in place around perimeter. Sign is up. Existing driveway to be entrance. Electric disconnected but wires still connected to poles. Photos added to PDox.