Permit / Edina← Search
#ED219837Building
7000 Cornelia Dr, Edina
IssuedMay 29, 2025
StatusUnknown
Value$814,050
Inspections5
Scope of work
Addition, Cornelia Elementary School Toilet Renovation
Location context
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$3,270.7
Total paid$3,270.7
Timeline
ApprovedMay 16, 2025
IssuedMay 29, 2025
Inspection record
Inspections5
Passed5
Failed0
- Dec 9, 2025
Fire Dept final
Approved, w/ CommentsInspectorBrian Hanrahan
-notification relocated to walls of bathrooms
- Aug 27, 2025
Fire Sprinkler Final (For appt: 952-826-0339)
ApprovedInspectorBrian Hanrahan
- Aug 27, 2025
Fire Dept final
Not ApprovedInspectorBrian Hanrahan
-FA strobes in bathrooms are wall mount design. To be switched out for ceiling mount appliances
- Aug 26, 2025
Building Final - COMMERCIAL
Partial ApprovalInspectorTedd Nelson
- Accessible restrooms require 48" in front of the water closet or 78" finish wall to finish wall or provide Architect drawing not providing all accessible restrooms. - Fire department final required
- Jul 16, 2025
Framing-Commercial
ApprovedInspectorTedd Nelson
- 4 bathroom groups and demising wall
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.