PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED220356

Building

5205 Minnehaha Blvd, Edina

IssuedJun 9, 2025
StatusUnknown
Value$8,000
Inspections19
Scope of work

Other Demolition (645-649), DEMO HOME - escrow paid

Location context
Parcel1802824440108
Coordinates44.90859, -93.33424
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$40
Total paid$40
Timeline
ApprovedMay 28, 2025
IssuedJun 9, 2025
Inspection record
Inspections19
Passed16
Failed0
  1. Jul 31, 2025

    Escrow

    Approved, w/ Comments

    InspectorLindsay Evans

    OK to issue escrow refund. Per Water Resources: Confirmed well on-site. Sealing record H416805 provided during plan review.
  2. Jul 31, 2025

    Building Final

    Approved, w/ Comments

    InspectorNate Borwege

    Escrow refund of $2500 Approved.
  3. Jul 29, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  4. Jul 29, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  5. Jul 23, 2025

    Demo Final

    Approved, w/ Comments

    InspectorLindsay Evans

    No inspection conducted for demo final so using the approved Footing inspection from New Home permit #ED220410 that Brian did on 7/23/25
  6. Jul 14, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  7. Jul 14, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Overall site looked good. Starting excavation for new home construction.
  8. Jul 11, 2025

    Escrow

    Progress Report

    InspectorLindsay Evans

    Received online escrow refund request. All of the required inspections have not been completed and have not started on new home construction yet. Will be able to continue working on escrow refund after the approved Footing inspection on New Home permit.
  9. Jul 1, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

  10. Jul 1, 2025

    Construction Fence

    Approved

    InspectorLindsay Evans

  11. Jun 16, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    Demo complete.
  12. Jun 16, 2025

    Construction Fence

    Approved, w/ Comments

    InspectorLindsay Evans

    Safety fence has been installed around entire perimeter of site. No steep slopes at this time.
  13. Jun 12, 2025

    Erosion Ctrl/Const Entrance

    Approved, w/ Comments

    InspectorLindsay Evans

    In process of demo
  14. Jun 10, 2025

    Erosion Ctrl/Const Entrance

    Approved

    InspectorLindsay Evans

    Not started yet
  15. Jun 5, 2025

    Tree Protection (call 952-826-0308)

    Approved

    InspectorLindsay Evans

  16. Jun 5, 2025

    Erosion Ctrl/Const Entrance

    Progress Report

    InspectorLindsay Evans

    Have not started demo yet
  17. May 27, 2025

    Preconstruction

    Approved, w/ Comments

    InspectorLindsay Evans

    Site looked good. EC in place (bio logs). Site sign up. Using existing driveway until demo is complete or until no longer sufficient. No IP installed due to location of CB and grade of the street.. Pre demo photos uploaded in PDox. Per Water Resources: Confirmed well on-site. Sealing record H416805 provided during plan review.
  18. May 27, 2025

    Tree Protection (call 952-826-0308)

    Progress Report

    InspectorLindsay Evans

    No tree protection had been installed at the time pre demo inspection conducted, however, all the metal posts had been installed around them and will likely be installed once the lot is a bit more clear (house demo'd and/or removal of trees that have been planned/approved to be removed)
  19. May 2, 2025

    Tree Plan

    Approved, w/ Comments

    InspectorLindsay Evans

    See tree escrow permit- NRMP ED220326, Preserving 9 trees, remove 4 no replacements. LB