Building
7200 France Ave S, Edina
New, Footing and Foundation
- Mar 24, 2026
Floor Slab
Partial ApprovalInspectorTedd Nelson
- Unit deck pour extension. level 1 east and north side
- Mar 24, 2026
CMU Fdn Reinforcement
Partial ApprovalInspectorTedd Nelson
- CMU grout at level 1 west perimeter wall
- Mar 24, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorTedd Nelson
- Mar 12, 2026
CMU Fdn Reinforcement
Partial ApprovalInspectorTedd Nelson
- CMU grouting level -1 level at Grids; 3 to 5
- Mar 12, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorTedd Nelson
- Mar 12, 2026
Floor Slab
Partial ApprovalInspectorTedd Nelson
- Unit deck pour extension. level 2. 5 pours on east side
- Mar 10, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorPeter Akmenkalns
- Mar 10, 2026
CMU Fdn Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
level 2 misc concrete infills to plane out for framing
- Mar 3, 2026
Floor Slab
Partial ApprovalInspectorPeter Akmenkalns
ramp to p2 D-G 1-3
- Mar 3, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorPeter Akmenkalns
- Feb 24, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorPeter Akmenkalns
- Feb 24, 2026
Floor Slab
Partial ApprovalInspectorTedd Nelson
- Vapor barrier for slab on grade, -2 level at Grids: 3 to 5 and G to M
- Feb 17, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorPeter Akmenkalns
- Feb 17, 2026
Floor Slab
Partial ApprovalInspectorPeter Akmenkalns
P2 level slab on grade and vapor barrier 1-5 A-G
- Feb 10, 2026·1:00 PM - 2:00 PM
Poured Foundation Reinforcement
scheduledInspectorTedd Nelson
- Feb 10, 2026
Floor Slab
Partial ApprovalInspectorTedd Nelson
- Vapor barrier for slab on grade, -2 level at Grids: 5 to7 and A to M
- Feb 6, 2026
Floor Slab
Partial ApprovalInspectorPeter Akmenkalns
7.5 A-H P2 level slab on grade
- Feb 6, 2026
Erosion Ctrl/Const Entrance
Partial ApprovalInspectorPeter Akmenkalns
- Jan 7, 2026
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
last of exterior foundation below grade G-J on 1
- Oct 30, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
wall foundation section L-K 1
- Oct 24, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- 3rd level foundation wall at Grid: K; 1 to 4...38'
- Oct 22, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- Lower level foundation wall at Grid: K; 1 to 4
- Oct 17, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
FOUNDATION WALL 1 C-G
- Oct 14, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
- lower level foundation 9-5 M
- Oct 9, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- Lower level foundation wall at Grid: 10; K to M and M; 10 to 7.5
Show 15 earlier inspections
- Oct 6, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- Lower level foundation wall at Grid: 10; F to K
- Oct 1, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- Lower level foundation wall at Grid: 10; B to F
- Sep 26, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorTedd Nelson
- Lower level foundation wall at Grid: A; 6.5 to 10
- Sep 23, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
foundation wall section along A 4-7
- Sep 19, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
-N W corrner 2 wall sections - 1 A- C - A 1-4
- Sep 17, 2025
Footing
CancelledInspectorPeter Akmenkalns
- Sep 16, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Pads at Grids: H6, H5, H4, H3, H2, J6, J5, J4, J3, J2 - Cont. at Grid: 1; L to G
- Sep 12, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Continuous at Grids: M; 9-1 - Pads at Grids: L8, L7, L6. K.8-4, K.8-2 and Stairs L-L.8 to 5-5.25
- Sep 9, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Continuous at Grid: 1; B to G and 3; B.5 to G - Pads at Grids: 4E, 4F, 4G, and E; 5 to 6
- Sep 8, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Pads at Grids: 7E, 7F, 7G, 6F, 6G, 5F, 5G
- Sep 5, 2025
Footing
Partial ApprovalInspectorPeter Akmenkalns
- (3)pad E-G on grid 8
- Sep 5, 2025
Poured Foundation Reinforcement
Partial ApprovalInspectorPeter Akmenkalns
-elevator pit walls
- Sep 4, 2025
Footing
Partial ApprovalInspectorPeter Akmenkalns
- strip perimeter footing A-M - pads 10 total D 1-9 and 2 on 9D 9E
- Sep 3, 2025
Footing
Partial ApprovalInspectorPeter Akmenkalns
-elevator pit footings area H-K 8-7 and 1 Pad all poured as 1 with elevatorpit - 5 pads along L-F on 9
- Aug 29, 2025
Footing
Partial ApprovalInspectorTedd Nelson
- Continuous with pads at Grid: A; 1 to 10 - Pads, Grids: B; 1 to 10 - Continuous, Grids: 1; A-B.5 and 10; A-B.5
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.