PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED222124

Building

5905 Long Brake Tr, Edina

IssuedJul 3, 2025
StatusUnknown
Value$850,000
Inspections11
Scope of work

Addition, Interior/exterior remodel with Addition

Location context
Parcel0811621330123
Coordinates44.86562, -93.37299
Loading map…
199 nearby
This permitNearby
Fees & payments
Total fees$4,250
Total paid$4,250
Timeline
ApprovedJul 3, 2025
IssuedJul 3, 2025
Inspection record
Inspections11
Passed9
Failed0
  1. Sep 29, 2025

    Footing

    Approved

    InspectorTedd Nelson

    - The footing under the existing addition was completed on 7/16/2025
  2. Sep 10, 2025

    Insulation

    Approved

    InspectorBrian Crask

  3. Sep 10, 2025

    Framing

    Partial Approval

    InspectorBrian Crask

    Framing in the house is approved. -Need to verify that the new footings & foundation under the existing attached shed are code compliant. These inspections were missed.
  4. Sep 8, 2025

    Insulation

    Partial Approval

    InspectorBrian Crask

    Approved pending Framing & MECH RI inspection approval.
  5. Sep 5, 2025

    Framing

    Not Approved

    InspectorBrian Crask

    -Need to verify that the new footings & foundation under the existing attached shed are code compliant. These inspections were missed. -Need MECH Rough-in for 5 supplies & one interior fireplace -Interior braced walls are TBD at a later date.
  6. Aug 26, 2025

    Footing

    Partial Approval

    InspectorPeter Akmenkalns

    3 holes in back for landing, 2 have slop and water 1 was ok
  7. Aug 15, 2025

    Framing

    Not Approved

    InspectorBrian Crask

    -Need to verify that the new footings & foundation under the existing attached shed are code compliant. These inspections were missed. -Need MECH & electrical Rough-ins -Interior braced walls are TBD at a later date.
  8. Aug 6, 2025

    Bldg Progress

    Progress Report

    InspectorBrian Crask

    -Need approved plan on-site -Contractor planning to get revised plan from engineer to include changes made and also have him specify that his structural plan incorporates the elevator company's framing specs.
  9. Jul 18, 2025

    Poured Foundation Reinforcement

    Approved

    InspectorBrian Crask

  10. Jul 16, 2025

    Footing

    Approved

    InspectorTedd Nelson

    - 3 deck footing, strip for the mechanical addition and elevator
  11. Jul 15, 2025

    Footing

    Cancelled

    InspectorGodwin Annin

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.