Building
5609 Heather La, Edina
New, NEW HOME
- Feb 10, 2026·10:00 AM - 10:30 AM
Final As Built Survey
scheduledInspectorScot Jandro
- Feb 3, 2026
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Nov 26, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
Fall Inspection Site is OK (Inspected by Drew Hollister)
- Nov 20, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Fall Inspection Repair/Re-establish biolog perimeter control Make sure site & street of clear of trash/debris Move materials out of city ROW (Inspected by Francis Killen)
- Nov 14, 2025
Insulation
ApprovedInspectorBrian Crask
Garage tuck pictures have been submitted and approved.
- Nov 13, 2025
Insulation
Partial ApprovalInspectorBrian Crask
Garage tuck is still TBD. Everything else is approved.
- Nov 13, 2025
Framing-New Home
ApprovedInspectorBrian Crask
- Nov 10, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorScot Jandro
- Nov 10, 2025
Framing-New Home
Partial ApprovalInspectorScot Jandro
-missing bearing at utility room inner corner for roof girder -A4 truss in garage missing bracing -connect top plates at rear dinning room door -Connect two center beams together at basement
- Nov 10, 2025
Weather Barrier/Flashing
ApprovedInspectorScot Jandro
- Oct 2, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Sep 30, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorPeter Akmenkalns
- Sep 30, 2025
Floor Slab
ApprovedInspectorPeter Akmenkalns
- Sep 12, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Sep 8, 2025
Erosion Ctrl/Const Entrance
Not ApprovedInspectorLindsay Evans
Need to clean street around existing driveway area and along the other side of the site along curbline Some of the bio logs in the front of the site are covered in sediment - dig out or install additional row to prevent sediment runoff over logs
- Sep 8, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 29, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Aug 29, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 28, 2025
Foundation Pre-Backfil
ApprovedInspectorTedd Nelson
- Aug 26, 2025
Foundation Pre-backfil (Top of foundation survey)
ApprovedInspectorPeter Akmenkalns
as proposed matches exactly in photos for refrence
- Aug 22, 2025
Poured Wall/Column (above grade)
ApprovedInspectorPeter Akmenkalns
- Aug 14, 2025
Footing
ApprovedInspectorPeter Akmenkalns
- Aug 13, 2025
Footing
Not ApprovedInspectorBrian Crask
Do Not Pour -Bottom of forms are filled with 1" rock that has been added over the native soils. Can not see soils to confirm that they are suitable to support the structure. Also, any rock added in the forms needs to be specified by a soils engineer. -Forms are not ready for inspection.
- Aug 11, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 11, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
Show 2 earlier inspections
- Aug 7, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Aug 7, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans