PULLFIRST[THE RECORD]
Permit / Edina← Search
#ED223488

Building

10 Southdale Ctr 2155a, Edina

IssuedOct 9, 2025
StatusUnknown
Value$721,804
Inspections9
Scope of work

New Tenant Finish, Tenant Fit Out

Location context
Fees & payments
Total fees$1,750
Total paid$1,750
Timeline
ApprovedSep 30, 2025
IssuedOct 9, 2025
Inspection record
Inspections9
Passed7
Failed0
  1. Dec 12, 2025

    Fire Dept final

    Approved

    InspectorBrian Hanrahan

  2. Dec 12, 2025

    Smoke Control

    Progress Report

    InspectorBrian Hanrahan

    -air flow is there but low -to be resolved with restaurant Smithson buildout behind store. Ductwork runs through that buildout wiith plans to be reconfigured twice
  3. Dec 12, 2025

    Building Final - COMMERCIAL

    Progress Report

    InspectorTedd Nelson

    - Address, signage for the front door and the door hardware is complete
  4. Dec 9, 2025

    Gypsum/FR Construction

    Approved

    InspectorTedd Nelson

  5. Dec 9, 2025

    Building Final - COMMERCIAL

    Partial Approval

    InspectorTedd Nelson

    - Mechanical and Electrical final required - Install the Address - Provide signage for the front door - Install door hardware
  6. Nov 18, 2025

    Above Ceiling Grid

    Approved

    InspectorTedd Nelson

  7. Nov 18, 2025

    Framing-Commercial

    Approved

    InspectorTedd Nelson

  8. Oct 31, 2025

    Fire Sprinkler Final (For appt: 952-826-0339)

    Approved

    InspectorBrian Hanrahan

  9. Oct 29, 2025

    Framing-Commercial

    Not Approved, Not Ready

    InspectorPeter Akmenkalns

    need all MEP and sprinkler RI completed.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.