Permit / Edina← Search
#ED225120

Building

4364 Vernon Ave, Edina

IssuedOct 16, 2025
StatusUnknown
Value$160,000
Inspections14
Scope of work

Alteration/Remodel, Interior kitchen remodel & exterior deck addition

Location context
Parcel2811721210017
Coordinates44.92042, -93.34993
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$800
Total paid$800
Timeline
ApprovedOct 7, 2025
IssuedOct 16, 2025
Inspection record
Inspections14
Passed14
Failed0
  1. Mar 27, 2026

    Footing

    Approved

    InspectorGodwin Annin

    - Helical pier report received via email.
  2. Mar 23, 2026

    Floor Slab

    Approved

    InspectorBrian Crask

    Under-slab Poly/Vapor Barrier is Approved
  3. Mar 16, 2026

    Footing

    Partial Approval

    InspectorGodwin Annin

    - underpinning Engineer letter received and Approved. - Helical pier report to be provided by Contractor not ready.
  4. Mar 16, 2026

    Poured Wall/Column (above grade)

    Approved

    InspectorBrian Crask

  5. Mar 16, 2026

    Foundation Pre-Backfil

    Approved

    InspectorBrian Crask

    Waterproofing is completed. Unconditioned space with no foundation insulation requirement. Sandy soils with no drain tile requirements.
  6. Mar 11, 2026

    Poured Wall/Column (above grade)

    Partial Approval w/ Comments

    InspectorBrian Crask

    Approved pending approval of engineering for section of footing that is under-pinned.
  7. Mar 4, 2026

    Footing

    Partial Approval

    InspectorGodwin Annin

    - Strip footing ok - Contractor to provide Engineer letter for the underpinning - Contractor to provide helical pier report
  8. Feb 26, 2026

    Footing

    Not Approved

    InspectorRick Chase

    Spoke with Kara Thanks for the discussion this morning, we look forward to receiving confirmation on the dowels to the existing footing and having the S1 plan revised/resubmitted for the proposed foundation changes.
  9. Feb 23, 2026

    Footing

    Not Approved

    InspectorGodwin Annin

    Footing inspection on 11/21/2025 was failed and a re inspection was required. - Contractor to provide a letter from Structural Engineer of records that states: 1. Footing and foundation underpinning are in substantial compliance with the structural design drawings. 2. Footings are compliant with R403.1.4.1. No additional work until letter received and approved by City of Edina. This is only the first section of strip footing.
  10. Feb 20, 2026

    Footing

    Not Approved

    InspectorPeter Akmenkalns

    footing are already poured. hole has been excavated for the winter and blankets were only on top of footing not protecting the sides. the ground was left to freeze under the footings. also not sure the minimum frost deepth have be achived.
  11. Nov 25, 2025

    Insulation

    Approved

    InspectorScot Jandro

  12. Nov 25, 2025

    Framing

    Approved

    InspectorBrian Crask

  13. Nov 24, 2025

    Framing

    Not Approved

    InspectorBrian Crask

    -Need header for opening at staircase.
  14. Nov 21, 2025

    Footing

    Not Approved

    InspectorGodwin Annin

    - Contractor to submit revised plan for review and reschedule

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.