Building
5513 Brookview Ave, Edina
New, New Home with deck
- Apr 10, 2026·8:30 AM - 9:00 AM
Lath
scheduledInspectorTedd Nelson
- Mar 20, 2026
Insulation
ApprovedInspectorRick Chase
Exterior Walls and Rim
- Mar 20, 2026
Framing-New Home
ApprovedInspectorRick Chase
Corrections completed.
- Mar 17, 2026
Framing-New Home
Not ApprovedInspectorBrian Crask
-Add anchor bolt in garage within 1' of butt end of bottom plate. -Header directly in front of front door is not correct / not an LVL, per plan
- Mar 17, 2026
Weather Barrier/Flashing
ApprovedInspectorBrian Crask
- Mar 5, 2026
Insulation
Partial ApprovalInspectorPeter Akmenkalns
spray foam behind fireplaces only
- Mar 5, 2026
Weather Barrier/Flashing
ApprovedInspectorPeter Akmenkalns
- Feb 4, 2026
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Feb 4, 2026
Construction Fence
Approved, w/ CommentsInspectorLindsay Evans
No longer needed
- Jan 15, 2026
Floor Slab
ApprovedInspectorPeter Akmenkalns
- Jan 15, 2026
Erosion Ctrl/Const Entrance
ApprovedInspectorPeter Akmenkalns
- Dec 19, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Dec 19, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Dec 11, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Dec 11, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Dec 11, 2025
Foundation Pre-backfil (Top of foundation survey)
ApprovedInspectorGodwin Annin
- Dec 4, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Dec 4, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Nov 25, 2025
Erosion Ctrl/Const Entrance
ApprovedInspectorLindsay Evans
- Nov 25, 2025
Foundation Pre-Backfil
ApprovedInspectorGodwin Annin
- Nov 25, 2025
Construction Fence
ApprovedInspectorLindsay Evans
- Nov 19, 2025
Poured Wall/Column (above grade)
ApprovedInspectorGodwin Annin
- Nov 17, 2025
Footing
ApprovedInspectorTedd Nelson
- Nov 17, 2025
Erosion Ctrl/Const Entrance
Progress ReportInspectorLindsay Evans
Seasonal Inspection - overall site looks good, site sign is up, no IP to remove - Should install double row of bio log around stockpile if it will be there for a while ( I will check back after foundation has been backfilled) - Clean up street at end of day as there is some trackout present
- Nov 13, 2025
Shoring needs to be done before footing inspection
ApprovedInspectorPeter Akmenkalns
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.