#ED220545

Building

5801 Fairfax Ave, Edina

IssuedDec 9, 2025
StatusUnknown
Value$150,000
Inspections14
Scope of work

Addition, Tear down current structure down to foundation.MUST LEAVE MIN 50% OF OLD EXTERIOR WALLS

Location context
Parcel1902824310021
Coordinates44.89803, -93.34034
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$750
Total paid$750
Timeline
ApprovedDec 2, 2025
IssuedDec 9, 2025
Inspection record
Inspections14
Passed13
Failed0
  1. Apr 9, 2026

    Insulation

    Not Approved

    InspectorBrian Crask

    -House-wrap requires full approval before insulation inspection can be fully approved. Contractor has been notified and is planning to call for WRB inspection. Insulation is approved pending house-wrap inspection.
  2. Apr 9, 2026

    Framing

    Partial Approval

    InspectorBrian Crask

    Outstanding Items need for full framing approval: Deck framing & footings are TBD and to be inspected at a later date. Approval: House framing is now approved Note: photo submitted of one remaining item clearly showing compliance. -Deck is TBD and to be inspected at a later date.
  3. Apr 7, 2026

    Framing

    Not Approved

    InspectorBrian Crask

    -Missing stringer header bearing. -Deck TBD at a later date
  4. Apr 6, 2026

    Insulation

    Partial Approval

    InspectorGodwin Annin

    - Contractor to reschedule for framing inspection before sheet rocking the entire house.
  5. Apr 2, 2026

    Framing

    Partial Approval

    InspectorBrian Crask

    -Missing center bearing wall headers in basement -Need full bearing to foundation at gaps under bottom plate at basement center bearing wall. -Contractor planning to add L bracket to stringer header for bearing. -Dec TBD at a later date. Notre: Okay to insulate.
  6. Mar 31, 2026

    Framing

    Not Approved

    InspectorBrian Crask

    -Missing LVL rim board. Contractor planning to get revised plans for all related engineering. -Missing stringer attachment to stringer header, not per engineered design. -Missing 3ply studs at stairwell -Missing rim board at stair well -Missing center bearing wall headers in basement -Contractor planing to add L-Bracket rated for use as a joist hanger at connection to LVL beam in basement. -Missing one bottom plate anchor bolt in garage -Deck TBD at a later date
  7. Mar 9, 2026

    Footing

    Approved

    InspectorBrian Crask

    Pad footing now approved Note: All footings are now approved.
  8. Mar 9, 2026

    Framing

    Partial Approval

    InspectorBrian Crask

    Partial inspection on roof trusses only. Roof trusses are approved.
  9. Mar 9, 2026

    Weather Barrier/Flashing

    Progress Report

    InspectorBrian Crask

    95% of the WRB is installed and per code. Contractor states that siding crew is planning to install drip caps for windows and patch in remaining WRB per their typical process.
  10. Feb 27, 2026

    Footing

    Not Approved

    InspectorBrian Crask

    -Pad footing form size & location is per engineering by MN P.E.. Thomas A. Webber Dated 12/17/2025. Contractor found an existing 4" drain line running through the new pad footing location. Contractor is planning to remove the pipe running through the footing, then get a re-inspection.
  11. Dec 22, 2025

    Foundation Pre-Backfil

    Approved

    InspectorScot Jandro

  12. Dec 22, 2025

    CMU Fdn Reinforcement

    Approved

    InspectorScot Jandro

  13. Dec 12, 2025

    Footing

    Approved

    InspectorScot Jandro

    Received picture of scrapped footing
  14. Dec 10, 2025

    Footing

    Partial Approval

    InspectorScot Jandro

    dewater lower footing, scrape out muck 20x8 w/#4 rebar

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.