PULLFIRST[THE RECORD]
Permit / Eden Prairie← Search
#EP192148

Building

10294 Lee Dr, Eden Prairie

IssuedSep 19, 2024
StatusUnknown
Value$298,394
Inspections23
Scope of work

New, NEW SF/BSMT FIN/FRONT ENTRY PORCH

Location context
Parcel2511622430018
Coordinates44.82028, -93.40750
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$5,163.39
Total paid$5,163.39
Timeline
ApprovedSep 19, 2024
IssuedSep 19, 2024
Inspection record
Inspections23
Passed23
Failed0
  1. Sep 3, 2025

    Bldg Final 1 Hour

    Pass

    InspectorTerry Enstad

  2. Mar 18, 2025

    Foundation Insul

    Pass

    InspectorTerry Enstad

  3. Mar 18, 2025

    Bldg Final 1 Hour

    Pass

    InspectorMike Uttenhove

    Ok to issue temp CO with following corrections. Caulk all windows-Protect foundation insulation-Driveway and sidewalk needs to be completed-Egress window well needs to be filled and drain tile cleaned of gravel. Final grade
  4. Mar 18, 2025

    Ice/Water Barrier (Photo`s on-site)

    Pass

    InspectorMike Uttenhove

  5. Mar 18, 2025

    Draintile

    Pass

    InspectorTerry Enstad

  6. Mar 18, 2025

    Foundation/Pre-Backfill

    Pass

    InspectorTerry Enstad

  7. Mar 17, 2025

    Bldg Final 1 Hour

    Partial Pass

    InspectorMike Uttenhove

    No cauking at several windows, Need to protect foundation insulation, Egress window well needs fill and drain is full of rock,Final grade not done,Driveway and sidewalk not in.
  8. Mar 17, 2025

    Blower Door Test

    Pass

    InspectorMike Uttenhove

  9. Jan 3, 2025

    Basement Insulation

    Pass

    InspectorTerry Enstad

  10. Jan 3, 2025

    Insulation

    Pass

    InspectorTerry Enstad

  11. Jan 3, 2025

    Window/Door Insulation

    Pass

    InspectorTerry Enstad

  12. Dec 31, 2024

    Framing 1 Hour

    Pass

    InspectorMike Uttenhove

  13. Dec 31, 2024

    Basement Framing

    Pass

    InspectorMike Uttenhove

  14. Dec 27, 2024

    Framing 1 Hour

    Partial Pass

    InspectorMike Uttenhove

    Pass pending electrical work completion and inspection
  15. Dec 27, 2024

    Basement Framing

    Partial Pass

    InspectorMike Uttenhove

    Pass pending completion of electrical work and inspection
  16. Dec 27, 2024

    Exterior Weather Barrier ( On-site ) + Photos

    Pass

    InspectorMike Uttenhove

  17. Dec 27, 2024

    Basement Ceiling Mech Rough-in

    Pass

    InspectorMike Uttenhove

  18. Dec 27, 2024

    Pan Flashing

    Pass

    InspectorMike Uttenhove

  19. Nov 20, 2024

    Under Slab/Radon

    Pass

    InspectorTerry Enstad

  20. Oct 9, 2024

    Foundation Wall Pour

    Pass

    InspectorTerry Enstad

  21. Oct 4, 2024

    Erosion Control

    Pass

    InspectorTerry Enstad

  22. Oct 4, 2024

    Footing

    Pass

    InspectorTerry Enstad

  23. Oct 4, 2024

    Porch Footing

    Pass

    InspectorTerry Enstad

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.