PULLFIRST[THE RECORD]
Permit / Eden Prairie← Search
#EP196472

Building

10200 Yellow Circle Dr 10250, Eden Prairie

IssuedMay 6, 2025
StatusUnknown
Value$6,037,741
Inspections15
Scope of work

New, New shell warehouse building

Location context
Parcel0111622120013
Coordinates44.89229, -93.41249
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$59,668.52
Total paid$59,668.52
Timeline
ApprovedApr 28, 2025
IssuedMay 6, 2025
Inspection record
Inspections15
Passed14
Failed0
  1. Dec 23, 2025

    Above Ceiling - Commercial Only

    Pass

    InspectorMike Uttenhove

  2. Dec 10, 2025

    Under Slab/Radon

    Pass

    InspectorMike Uttenhove

  3. Dec 8, 2025

    Under Slab/Radon

    Partial Pass

    InspectorMike Uttenhove

    South west corner, under mezzanine area is good.
  4. Oct 24, 2025

    Footing

    Pass

    InspectorMike Uttenhove

  5. Oct 21, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    Interior loading dock area is good.
  6. Sep 15, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    Footings for loading dock retaining wall at grid lines A-1.5 and A-5.5 are good.
  7. Sep 15, 2025

    Foundation Wall Pour

    Pass

    InspectorMike Uttenhove

    Loading dock
  8. Aug 15, 2025

    Foundation/Pre-Backfill

    Pass

    InspectorMike Uttenhove

  9. Aug 14, 2025

    Framing

    Pass

    InspectorMike Uttenhove

  10. Jul 23, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    All perimeter footings are complete.
  11. Jul 18, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    East side from grid 8c to 8a is good and grid line 7 to 8 on the North side is good.
  12. Jul 15, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    From grid line 4.5 to grid line 8 on south side and from 8F to 8C on East side is good.
  13. Jul 14, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    (4) Pad footings on grid line 2 and (4) pad footings on grid line 3 are good.
  14. Jul 9, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    Good from grid line1 to linefrom grid line 1 to line 4 on the south side of building. 2.5 on the north side of building, all of grid line 1 and
  15. Jul 8, 2025

    Footing

    Call for Re-inspection

    InspectorMike Uttenhove

    Not ready

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.