Permit / Eden Prairie← Search
#EP200281

Building

9025 Aztec Dr, Eden Prairie

IssuedNov 6, 2025
StatusUnknown
Value$3,550,000
Inspections16
Scope of work

New, NEW BLDG FOR 15 UNIT ASSISTED LIVING/DEMENTIA CARE FACILITY & RETAINING WALL

Location context
Parcel2311622320014
Coordinates44.84074, -93.43804
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$154,708.55
Total paid$154,708.55
Timeline
ApprovedNov 4, 2025
IssuedNov 6, 2025
Inspection record
Inspections16
Passed15
Failed1
  1. Apr 6, 2026

    Framing 1 Hour

    Partial Pass

    InspectorStephen Kartak

    Framing ok. Provide structural engineers inspection report
  2. Apr 6, 2026

    Firewall

    Pass

    InspectorStephen Kartak

    Fire stopping and fire caulking
  3. Apr 6, 2026

    Erosion Control

    Pass

    InspectorStephen Kartak

  4. Feb 23, 2026

    Framing 1 Hour

    Partial Pass

    InspectorStephen Kartak

    Framing inspection for main corridors. OK to sheet rock corridor side of walls and horizontal mech shafts.
  5. Feb 6, 2026

    Under Slab/Radon

    Partial Pass

    InspectorStephen Kartak

    South 1/3 of slab. Ok to pour
  6. Feb 5, 2026

    Under Slab/Radon

    Partial Pass

    InspectorStephen Kartak

    North 1/3 of slab ok to pour. Note:CVT was onsite this morning to perform a more thorough frost check around interior building perimeter. A hand auger was used to probe the interior perimeter subgrade soils to depths of approximately 3' to reveal the underlying material. No frost or frozen soil was observed in hand auger borings. Concrete Concepts onsite surface tamping subgrade. CVT project engineer was informed of soil and subgrade conditions and approved soils for concrete placement.
  7. Jan 13, 2026

    Ice/Water Barrier (Photo`s on-site)

    Partial Pass

    InspectorMike Uttenhove

    South half of building is good. North half not started. Will have photos
  8. Jan 9, 2026

    Framing 1 Hour

    Partial Pass

    InspectorStephen Kartak

    Roof sheathing ok. Ok to install roofing material Provide gable truss fix at framing inspection
  9. Dec 5, 2025

    Footing

    Fail

    InspectorStephen Kartak

    Not ready
  10. Nov 20, 2025

    Retaining Wall Final

    Pass

    InspectorStephen Kartak

  11. Nov 19, 2025

    Foundation/Pre-Backfill

    Pass

    InspectorStephen Kartak

  12. Nov 19, 2025

    Foundation Insul

    Pass

    InspectorStephen Kartak

  13. Nov 18, 2025

    Foundation Wall Pour

    Pass

    InspectorMike Uttenhove

  14. Nov 14, 2025

    Exterior/Interior Wall Bracing

    Pass

    InspectorStephen Kartak

    On site with Mike
  15. Nov 14, 2025

    Foundation Wall Pour

    Partial Pass

    InspectorMike Uttenhove

    Starting at vestibule going North and stopping at the North side of patio area.
  16. Nov 12, 2025

    Footing

    Partial Pass

    InspectorMike Uttenhove

    All perimeter footings are good to pour