PULLFIRST[THE RECORD]
Permit / Apple Valley← Search
#AV129304

Building

7577 138th St W, Apple Valley

IssuedSep 4, 2024
StatusUnknown
Value$357,450
Inspections20
Scope of work

Dwelling, 3440 SF Total/1278 SF 1st Floor/1720 SF 2nd Floor/ 442 SF Garage

Location context
Parcel017595107050
Coordinates44.75011, -93.21910
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$658.63
Total paid$658.63
Timeline
ApprovedAug 30, 2024
IssuedSep 4, 2024
Inspection record
Inspections20
Passed4
Failed1
  1. Feb 4, 2026

    Final - 30 minutes

    Compliant

    InspectorChris Pequin

  2. Jan 27, 2026

    Final - 30 minutes

    Non-Compliant

    InspectorChris Pequin

    Stair risers cannot have a variance of more than 3/8 inch from the lowest rise to largest rise for a flight of stairs (7 1/4 and 7 3/4 present). Discussed alternative options approved by the building official for a landing at base of stairs to accommodate 8 1/2 rise at bottom of stairs.
  3. Jan 26, 2026

    Final - 30 minutes

    Non-Compliant

    InspectorChris Pequin

    Landing at base of stairs only measures 24 inches deep. Updated survey required and dispute with neighbor regarding retaining wall must be resolved. Tempered film on window must be verified.
  4. Oct 3, 2025

    Final - 30 minutes

    Non-Compliant

    InspectorChris Andrejka

    stair risers must be within 3/8" of all stairs on a run and no more than 7 3/4" high. a continuous handrail is required on the stairs. window fall protection is required on all windows on the second level that sills sit under 24" above the floor. the picture window in the owner bathroom must be tempered. the roof venting at the ridge must have the aggregate openings verified. the venting at the ridge must be 1sq ft per 150 sft of roof area.
  5. Jun 3, 2025

    Lath

    Pass

    InspectorCraig Schultz

    corrections are made
  6. Jun 2, 2025

    Lath

    Non-Compliant

    InspectorCraig Schultz

    1. the lath on the left side of the walk door is sideways, not the correct direction, change. 2. tape the edges of the D paper through the corners to the brick mold on both sides of the walk door. call for reinspection
  7. May 1, 2025

    Lath

    Fail

    InspectorCraig Schultz

    1. need self-furring lath, this is not. 2. need 2 layers of grade D paper, this in not. Remove what is here and install correct material and call for reinspection. Install D paper with label visible for inspection
  8. Apr 2, 2025

    Insulation

    Compliant

    InspectorChris Pequin

    Batt/poly throughout with sprayfoamed rims and net and blown floors.
  9. Mar 24, 2025

    Framing - 60 minutes

    Compliant

    InspectorChris Pequin

    engineered fixes provided from truss company
  10. Mar 18, 2025

    Framing - 60 minutes

    Non-Compliant

    InspectorChris Pequin

    Anchor bolts missing within 12 inches of ends of bottom plates and in intervals exceeding 6 feet. Missing PF straps on garage door. Missing joist hanger nails in some hangers for floor of upstairs deck (visible on main level). Sleepers require 3 toenailed nails. Missing nail plate at bottom plate by laundry standpipe upstairs. Rafter tie missing upstairs by bathroom on West side of home. Missing rafter tie by NW corner. Roof truss A1SG is in the wrong location. Floor truss F1GT not laminated correctly and now not possible (need approval from truss company on fix). Missing joist hanger nails where F2GT is above stairs.
  11. Mar 13, 2025

    Ice & Water

    Partial Pass

    InspectorChris Pequin

    Digital submission of ice and water underlayment extending from eave to ridge across entire roof.
  12. Mar 5, 2025

    Wrap Inspection

    Compliant

    InspectorChris Pequin

  13. Feb 26, 2025

    Framing - 60 minutes

    Partial Pass

    InspectorChris Pequin

    Wall bracing as per plan
  14. Feb 21, 2025

    Framing - 60 minutes

    Non-Compliant

    InspectorChris Pequin

    Called for a wall bracing inspection. Entire home is CS WSP however whole home has staples for fasteners. 8D nails required 6" on edge and 12" in field.
  15. Oct 18, 2024

    Footing

    Compliant

    InspectorPatrick Devery

    Interior grade beam at stair wall.
  16. Sep 24, 2024

    Foundation/Water Proofing

    Compliant

    InspectorPatrick Devery

    Insulation added to top of slab, tapered at top.
  17. Sep 23, 2024

    As Built

    Compliant

    InspectorEvan Acosta

  18. Sep 17, 2024

    Poured Wall

    Compliant

    InspectorPatrick Devery

  19. Sep 17, 2024

    Footing

    Partial Pass

    InspectorPatrick Devery

    Everything but grade beam. Engineering for poured wall received.
  20. Sep 16, 2024

    Footing

    Correct and Proceed

    InspectorChris Pequin

    Footing layout has changed slightly by front entry but does not affect layout. New plans showing the change on Page A02 must be approved. Concrete contractor on site had engineering provided for step foundation due to elevation change. Engineering packet must be uploaded to project dox as well. Strip footing not completed yet and will require separate footing inspection. OK to pour perimeter footing. Revised plans required prior to strip footing. Contractor pouring at own risk.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.