Permit / Apple Valley← Search
#AV131194

Building

15720 Highview Dr, Apple Valley

IssuedJan 21, 2025
StatusUnknown
Value$100,000
Inspections12
Scope of work

Addition, 112 SF New - Two story addition on back side of home

Location context
Parcel014420204300
Coordinates44.72277, -93.24306
Loading map…
200 nearby
This permitNearby
Fees & payments
Total fees$325.63
Total paid$325.63
Timeline
ApprovedJan 21, 2025
IssuedJan 21, 2025
Inspection record
Inspections12
Passed3
Failed0
  1. Jun 24, 2025

    Final - 30 minutes

    Pass

    InspectorCraig Schultz

    corrections are made
  2. Jun 6, 2025

    Final - 30 minutes

    Non-Compliant

    InspectorCraig Schultz

    1. need a smoke detector in the upper floor master bedroom. 2. need a smoke detector on the main floor. 3. we need to check fall protection on all new openable windows also. Call for reinspection when ready carbon monoxide detectors are in place, flashing is in place over new windows, safety glass is in place in windows in addition
  3. Mar 26, 2025

    Framing - 60 minutes

    Compliant

    InspectorChris Pequin

    Received revised engineering and rafter connection on site matches.
  4. Mar 26, 2025

    Insulation

    Compliant

    InspectorChris Andrejka

  5. Mar 24, 2025

    Framing - 60 minutes

    Non-Compliant

    InspectorChris Pequin

    Energy heel now fixed however the structural engineer must sign off on the bearing of the rafters at the top plate. Still has tapered rafters at top plate now with 1/2 inch plywood gussets and vertical blocks to top plate.
  6. Mar 18, 2025

    Framing - 60 minutes

    Non-Compliant

    InspectorPatrick Devery

    The roof construction does not match approved plan sheets at eave. Although this area does have an attic space, we are willing to accept the reduction of R-value to that of Section R402.2.2 of R-30. This would require the ceiling height to drop 3". The chutes would need to be constructed to withstand any expansion of closed cell foam. Written verification required from the structural engineer for bearing of rafters at exterior wall.
  7. Mar 14, 2025

    Wrap Inspection

    Compliant

    InspectorChris Pequin

  8. Mar 14, 2025

    Framing - 60 minutes

    Non-Compliant

    InspectorChris Pequin

    Mechanical permit and RI inspection must be completed for new heat run extensions. Joist hangers on main level are not nailed in any of the bottom 2 nail holes. New roof eave missing energy heel. Beam point load not carried to basement to left of patio door in basement on south corner of home (where existing meets addition).
  9. Mar 14, 2025

    Porch Footings

    Not Applicable/Required

    InspectorChris Pequin

  10. Feb 25, 2025

    Footing

    Compliant

    InspectorChris Pequin

    Updated helical torque report received and updated plans from engineer.
  11. Feb 25, 2025

    Framing - 60 minutes

    Partial Pass

    InspectorChris Pequin

    Wall bracing and straps as per engineering
  12. Jan 27, 2025

    Porch Footings

    Partial Pass

    InspectorChris Andrejka

    Helical piers installed (four total) the plan called for three piers but the pier at the inside corner of the existing foundation was unable to be installed tight to the corner, the pier is 18" from the inside corner of the foundation. The installers added an additional pier on the adjacent wall 18" from the inside corner. All cmu cores have been filled along the two walls below the addition. Updated plans from the Engineer are required, a workflow into projectdox will be opened for updated plans to be submitted for review and approval. need helical report prior to final inspection.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.