PULLFIRST[THE RECORD]
Permit / Apple Valley← Search
#AV135589

Sewer & Water

311 Co Rd 42, Apple Valley

IssuedJul 15, 2025
StatusUnknown
Value$294,528
Inspections14
Scope of work

New

Location context
Fees & payments
Total fees$1,223.74
Total paid$1,223.74
Timeline
ApprovedJul 15, 2025
IssuedJul 15, 2025
Inspection record
Inspections14
Passed6
Failed0
  1. Feb 4, 2026

    Final

    Compliant

    InspectorChris Andrejka

  2. Sep 25, 2025

    Bacteria Test

    Compliant

    InspectorChris Andrejka

    second test received
  3. Aug 22, 2025

    5 lb Test

    Compliant

    InspectorChris Andrejka

    rain leaders between pool and building
  4. Aug 21, 2025

    Flushing

    Compliant

    InspectorChris Andrejka

    both fire and domestic lines flushed
  5. Aug 20, 2025

    5 lb Test

    Partial Pass

    InspectorChris Andrejka

    air on the sewer line from the street into the building
  6. Aug 19, 2025

    Flushing

    Non-Compliant

    InspectorChris Andrejka

    The valve was being operated without the city's utilities department on site. the contractor was told to stop the test and schedule someone from the utility department to come turn the valve for the flush.
  7. Aug 19, 2025

    5 lb Test

    Partial Pass

    InspectorChris Andrejka

    5# on pvc storm that passes over the 4" and 8" water lines. still need to test the roof drain line between the pool area and the building.
  8. Aug 13, 2025

    Underground/Rough In

    Compliant

    InspectorChris Andrejka

    underground for roof drains connecting with structure 20 all pvc. wye'd off for deck drains from pool area.
  9. Aug 12, 2025

    Hydrostatic Test

    Compliant

    InspectorChris Andrejka

  10. Aug 12, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    inverts mudded.
  11. Aug 11, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    HDPE from existing storm structure 10 to structure 11.
  12. Aug 8, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    storm structures 20 with hdpe to 21 with hdpe to outlet. 23 with hdpe to 22 and hdpe to outlet.
  13. Aug 7, 2025

    Curb Stop 1st Look

    Compliant

    InspectorChris Andrejka

    8" gate valve and 4" curb stop installed past the hydrant in the parking lot. water lines stubbed into building.
  14. Aug 7, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    schedule 40 sanitary ran from street into building. 8" water supply stubbed in just before hydrant in parking lot.