Permit / Apple Valley← Search
#AV133848Building
15555 English Ave, Apple Valley
IssuedAug 1, 2025
StatusUnknown
Value$792,614
Inspections17
Scope of work
Footings/Foundation
Location context
Fees & payments
Total fees$1,518.31
Total paid$1,518.31
Timeline
ApprovedAug 1, 2025
IssuedAug 1, 2025
Inspection record
Inspections17
Passed10
Failed0
- Dec 5, 2025
Poured Wall
CompliantInspectorChris Andrejka
- Nov 18, 2025
Poured Wall
Partial PassInspectorChris Andrejka
all foundation work associated with footing and foundation permit complete. waiting for fees to be paid for reviewing of updated plans to close out footing and foundation permit.
- Oct 8, 2025
Poured Wall
CompliantInspectorChris Andrejka
remaining wall ok to pour.
- Oct 6, 2025
Footing
CompliantInspectorChris Andrejka
remaining footings for retaining walls around volleyball court. There are revised plans that have been submitted for review.They show a portion of the wall on the exterior bar building being redone.
- Oct 2, 2025
Poured Wall
Partial PassInspectorChris Andrejka
retaining walls around the bags/cornhole courts and the south and west walls.
- Sep 30, 2025
Footing
Partial PassInspectorChris Andrejka
footings for south and west retaining walls on the exterior of the volleyball courts and around the bags/cornhole courts.
- Sep 26, 2025
Poured Wall
Partial PassInspectorChris Andrejka
wall between volleyball courts and outdoor seating area and column footings supporting overhang at covered patio.
- Sep 22, 2025
Footing
Partial PassInspectorChris Andrejka
footings for the retaining wall supporting the patio deck adjacent to the volleyball courts and the outbuilding.
- Sep 16, 2025
Poured Wall
Partial PassInspectorChris Andrejka
remaining exterior walls on main building.
- Sep 5, 2025
Foundation/Water Proofing
CompliantInspectorChris Andrejka
exterior drain tile at dropped portion of foundation at bowling lanes area. Horizontal perimeter insulation on interior of both buildings will be inspected under the full building permit when the slab is poured under permit AV133660.
- Sep 5, 2025
Poured Wall
Partial PassInspectorChris Andrejka
exterior wall poured wall from grid line G,1 east and down towards D,8.
- Sep 5, 2025
Footing
Partial PassInspectorChris Andrejka
remaining main building footings per approved plans.
- Sep 2, 2025
Foundation/Water Proofing
Partial PassInspectorChris Andrejka
the foundation on interior has rigid foam to bottom of footing.
- Aug 28, 2025
Footing
CompliantInspectorChris Andrejka
strip footings starting at grid line 1 between D.1 and E up to strip footings with pads starting on grid line 8 between grid lines D and E. the soils issue has been resolved the email chain with the EOR has been saved to laserfische.
- Aug 25, 2025
Poured Wall
Correct and ProceedInspectorGeorge Dorn
Need an email from the engineer of record indicating the thickness and type of rock added under the footings of the building. There was much water and muck on site do to hydrostatic water coming up from the soil. Contractor was pumping out all of the soil cuts around the perimeter. 4 interior pads ok located on grid 7.4 C, 7.0 D, 6 C, and 6 D. Poured wall ok from grid line J3 to grid line 1B
- Aug 25, 2025
Footing
Correct and ProceedInspectorGeorge Dorn
Need an email from the engineer of record indicating the thickness and type of rock added under the footings of the building. There was much water and muck on site do to hydrostatic water coming up from the soil. Contractor was pumping out all of the soil cuts around the perimeter. 4 interior pads ok
- Aug 7, 2025
Footing
Partial PassInspectorChris Andrejka
strip footings with pads starting on grid line 8 between grid lines D and E over to between grid lines 4 and 5 on line J. all interior pad footings not connected to the stirp footings.
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.