PULLFIRST[THE RECORD]
Permit / Apple Valley← Search
#AV135822

Sewer & Water

15555 English Ave, Apple Valley

IssuedAug 1, 2025
StatusUnknown
Value$120,000
Inspections12
Scope of work

New

Fees & payments
Total fees$512.54
Total paid$512.54
Timeline
ApprovedAug 1, 2025
IssuedAug 1, 2025
Inspection record
Inspections12
Passed7
Failed0
  1. Oct 7, 2025

    Bacteria Test

    Compliant

    InspectorCentral Maintenance Facility

    Bact. Test #2
  2. Oct 6, 2025

    Bacteria Test

    Compliant

    InspectorCentral Maintenance Facility

    Bact Test #1
  3. Oct 2, 2025

    Flushing

    Compliant

    InspectorChris Andrejka

  4. Sep 30, 2025

    Hydrostatic Test

    Compliant

    InspectorChris Andrejka

    test reading @200# after 2hrs
  5. Sep 29, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    storm sewer continued pvc from st-102 connecting to st-103, hdpe from st-103 to st-104.
  6. Sep 25, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    structure 100 connected to ex stub 1 with pvc. structure102 added and connected to the pvc from structure 101. pvc from structure 102 ran north to just before the parking entrance.
  7. Sep 23, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    storm structure 100 with hdpe to 101 from 101 to 102 with pvc. the pvc has not been run all the way to 102 also 102 is not yet installed.
  8. Sep 18, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    water supply for fire and domestic off branch for hydrant ran into building.
  9. Sep 17, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    all sanitary installed and ran into building except for the grease trap
  10. Sep 16, 2025

    Underground/Rough In

    Not Ready

    InspectorChris Andrejka

    waiting for supplies for 20' connection to sanitary.
  11. Sep 12, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    8" water supply line to hydrant in southwest corner of lot.
  12. Sep 11, 2025

    Underground/Rough In

    Partial Pass

    InspectorChris Andrejka

    8" water supply line started after the two 45 bends after where the water supply enters the site. continues south with 8" gate valve and 8"x8" tee for fire and domestic. line continues towards the hydrant at south west of lot approx 60' of line after the two 45 degree turns in the south east corner.

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.