Building
7169 153rd St W, Apple Valley
Footings/Foundation
- Mar 3, 2026
Footing
CompliantInspectorChris Pequin
- Mar 3, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
Last remaining piers as per plan. Work is now finished for footing and foundation permit however it is to remain open until concrete testing acceptance is provided by Chosen Valley Testing.
- Mar 2, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
All column piers except the 4 interior pads
- Mar 2, 2026
Footing
Partial PassInspectorChris Pequin
Interior footings 2-F4s and 2-F5s
- Feb 27, 2026
Footing
Partial PassInspectorChris Pequin
Pad footings at the following gridlines: D3, D.6-3, E.7-6, F.2-6, F.7-6, G.5-6, F.2-5, F.7-5, G.3-5, H.1-5, L-6.4
- Feb 27, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 26, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 26, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
Last remaining forms for exterior poured wall complete (and strip footing through center for interior LB precast)
- Feb 26, 2026
Footing
Partial PassInspectorChris Pequin
Pad footings inside elevator pit and 3 adjacent pad footings to East
- Feb 25, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 24, 2026
Footing
Partial PassInspectorChris Pequin
Last remaining strip footings except for trash enclosure. Still need to inspect interior pads.
- Feb 24, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 23, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 23, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
Poured wall A1-A2
- Feb 20, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
4 of 5 C2 piers on SW corner. Forms and reinforcement from gridlines: E4-K4, K4-K8, K8-E8
- Feb 20, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 20, 2026
Footing
Partial PassInspectorChris Pequin
Footing aside from trash enclosure footing from gridline: A1-A2
- Feb 19, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 18, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
Waterproofing membrane and rigid foam from A1-M3
- Feb 18, 2026
Footing
Partial PassInspectorChris Pequin
Interior precast footing at 2' and 2'-5" from gridline :D4-K4
- Feb 18, 2026·2:00 PM - 2:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 17, 2026
Footing
Partial PassInspectorChris Pequin
24"X12" continuous footings with 2 #5 from gridline M3-E8
- Feb 17, 2026·1:00 PM - 1:30 PM
Footing
scheduledInspectorChris Pequin
- Feb 17, 2026
Foundation/Water Proofing
Partial PassInspectorChris Pequin
A1-M3 12 inch poured wall with 2 EF horiz and vert at 16 OC. Need updated structural plans with reinforcement (plan on site only not in Pdox).
- Feb 13, 2026
Footing
Partial PassInspectorChris Pequin
24"X12" continuous footings with 2 #5 from gridline A1-M3
Show 1 earlier inspection
- Feb 13, 2026·2:00 PM - 3:00 PM
Footing
scheduledInspectorChris Pequin
Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.