PULLFIRST[THE RECORD]
Permit / Maple Grove← Search
#MG403058

Building

18135 100th Ct N, Maple Grove

IssuedJun 25, 2025
StatusUnknown
Value$600,000
Inspections19
Scope of work

New, No Sidewalks finished basement

Location context
Fees & payments
Total fees$2,413.78
Total paid$2,413.78
Timeline
ApprovedJun 12, 2025
IssuedJun 25, 2025
Inspection record
Inspections19
Passed8
Failed1
  1. Mar 2, 2026

    Grading

    Needs Correction

    InspectorShane Awalt

    No sod. Re-inspect once dirt is smoothed out and dirt pile on side yard is removed.
  2. Feb 3, 2026

    Final - 30

    Pass

    InspectorKen Nelson

  3. Jan 23, 2026

    Final - 30

    Partial Inspection

    InspectorKen Nelson

    OK to issue CO when electrical permit closes
  4. Jan 9, 2026

    Grading

    Needs Correction

    InspectorShane Awalt

    No sod. Snow on ground. Re-inspect once snow is gone and dirt pile in side yard is removed.
  5. Oct 28, 2025

    Lath (if required)

    Pass

    InspectorDylan DeMarais

    Passed via contractor provided pictures, no on-site inspection conducted. (Instructed to accept pictures by building official CC / KN)
  6. Oct 17, 2025

    Interior Braced Wall Panel

    Pass

    InspectorKen Nelson

  7. Oct 16, 2025

    Interior Braced Wall Panel

    Not Ready

    InspectorDylan DeMarais

  8. Oct 13, 2025

    Insulation

    Pass

    InspectorKen Nelson

    Open correction items: contractor will be sending in engineer's report
  9. Oct 8, 2025

    Insulation

    Cancel

    InspectorRobert Griffin

  10. Oct 3, 2025

    Framing 60

    Correction notice

    InspectorRobert Griffin

  11. Oct 1, 2025

    Framing 60

    Correction notice

    InspectorRobert Griffin

  12. Sep 12, 2025

    Sheathing

    Correction notice

    InspectorRobert Griffin

    Ok to check at framing
  13. Aug 27, 2025

    Underslab Vapor Barrier

    Pass

    InspectorRobert Griffin

  14. Jul 23, 2025

    Foundation-Exterior

    Pass

    InspectorDon Knutson

  15. Jul 17, 2025

    Poured Wall

    Pass

    InspectorKen Nelson

  16. Jul 14, 2025

    Footing

    Pass

    InspectorColby Cartney

  17. Jul 11, 2025

    Foundation-Exterior

    Not Ready

    InspectorDylan DeMarais

  18. Jul 8, 2025

    Poured Wall

    Cancel

    InspectorRobert Griffin

    Footings not yet poured.
  19. Jul 7, 2025

    Footing

    Failed

    InspectorColby Cartney

    need soil corrections

Data sourced from Minnesota Department of Labor & Industry, Minnesota Attorney General, federal OSHA, and municipal permit offices. Records are public and may not reflect pending appeals or corrections.